The DILG Albay Provincial Operations Office conducted a final inspection and evaluation of the completed FY 2023 Support to Barangay Development Program (SBDP) project, the Provision of Renewable Energy-Based Electrification and FY 2022 SBDP Construction of Farm-to-Market Road in Barangay Catomag and Barangay Cabaloaon, Guinobatan, Albay, respectively last January 26, 2024.
The activity was facilitated by Engr. III Clint Jake P. Borromeo, Engr. III Mark Joseph T. Obo, PEO II Arjun P. Delovino of DILG Albay and LGOO VI Josefa A. Escurel of DILG Guinobatan.
As of January 26, 2024, FY 2022 SBDP has 26 projects completed out of 26 total projects with a 100% completion rate. Meanwhile, the 2023 SBDP has a 21.05% completion rate with 12 completed projects out of 57 total sub-projects.